The Lake Report ~ November 4 - 10, 2002

Click here to see November 11 - 30, 2002

 

Monday - Guess what the weather brought!
The electrician arrived and hooked up new plugs, telephone jacks , our sump pump and submersed well pump
 

Also the plumber - drilling hole for water pipe into basement... Water pipe in, copper ground out to well
 

Here is our nice new well water tank, all hooked up! But not the tankless water heater yet
 

Our septic out pipe is now in place
 

On Tuesday Ken shovelled fill to cover the water pipe in from the well and the septic out pipe
 
Marilyn dug a trench for the sump pump drain
 

On Wednesday our duct/vents for the furnace were installed - they will be totally hidden above the ceiling
 

The backhoe fills the rest of the water pipe trench in...
 

and grades the yard
 
It is 13 below here Thursday - too cold for any workers.
We are without running water in the Nussey cottage and eagerly await the general contractor to install the basement windows and doors!
 

September 2002

Tuesday, October 1, 2002

Wednesday, October 2, 2002

Thursday, October 3, 2002

Friday, October 4, 2002

Monday, October 7, 2002

October 14 - 20, 2002

October 21 - 27, 2002

October 28 - November 3, 2002

November 11 - 30, 2002

Back