The Lake
Report ~ November 4 - 10, 2002
-

Monday - Guess what the weather brought!
The electrician arrived and hooked up new plugs, telephone jacks
, our sump pump and submersed well pump
-


Also the plumber - drilling hole for water pipe into basement...
Water pipe in, copper ground out to well
-

Here is our nice new well water tank, all hooked up! But not
the tankless water heater yet
-

Our septic out pipe is now in place
-


On Tuesday Ken shovelled fill to cover the water pipe in from
the well and the septic out pipe
-
- Marilyn dug a trench
for the sump pump drain
-


On Wednesday our duct/vents for the furnace were installed -
they will be totally hidden above the ceiling
-


The backhoe fills the rest of the water pipe trench in...
-

and grades the yard
-
- It is 13 below here Thursday
- too cold for any workers.
We are without running water in the Nussey cottage and eagerly
await the general contractor to install the basement windows
and doors!
-